WE1I3 FRIB Commissioning 118
 
  • P.N. Ostroumov, F. Casagrande, K. Fukushima, K. Hwang, M. Ikegami, T. Kanemura, S.H. Kim, S.M. Lidia, G. Machicoane, T. Maruta, D.G. Morris, A.S. Plastun, H.T. Ren, J. Wei, T. Xu, T. Zhang, Q. Zhao, S. Zhao
    FRIB, East Lansing, Michigan, USA
 
  Funding: Work supported by the U.S. Department of Energy Office of Science under Cooperative Agreement DE-SC0000661, the State of Michigan and Michigan State University.
The Facility for Rare Isotope Beams (FRIB), a major nuclear physics facility for research with fast, stopped and reaccelerated rare isotope beams, was successfully commissioned and is in operation. The acceleration of Xe, Kr, and Ar ion beams above 210 MeV/u using all 46 cryomodules with 324 superconducting cavities was demonstrated. Several key technologies were successful-ly developed and implemented for the world’s highest energy continuous wave heavy ion beams, such as full-scale cryogenics and superconducting radiofrequency resonator system, stripping of heavy ions with a thin liquid lithium film, and simultaneous acceleration of multiple-charge-state heavy ion beams. In December 2021, we demonstrated the production and identification of 84Se isotopes and, in January 2022, commissioned the FRIB fragment separator by delivering a 210 MeV/u argon beam to the separator’s focal plane. The first two user experiments with primary 48Ca and 82Se beams have been successfully conducted in May-June 2022.
 
slides icon Slides WE1I3 [6.543 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-HIAT2022-WE1I3  
About • Received ※ 21 June 2022 — Revised ※ 29 June 2022 — Accepted ※ 10 August 2022 — Issue date ※ 29 September 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TH1C3 Automation of RF and Cryomodule Operation at FRIB 136
 
  • S. Zhao, E. Bernal, W. Chang, E. Daykin, E. Gutierrez, W. Hartung, S.H. Kim, S.R. Kunjir, T.L. Larter, D.G. Morris, J.T. Popielarski, H.T. Ren, T. Xu
    FRIB, East Lansing, Michigan, USA
 
  Funding: Work supported by the U.S. Department of Energy Office of Science under Cooperative Agreement DE-SC0000661.
The Facility for Rare Isotope Beams (FRIB) has been commissioned, with rare isotopes first produced in December 2021 and first user experiments conducted in May 2022. The FRIB driver linear accelerator (linac) uses 6 room temperature cavities, 324 superconducting cavities, and 69 superconducting solenoids to accelerate ions to more than 200 MeV/nucleon. Because of the large scale, automation is essential for reliable linac operation with high availability. Automation measures implemented during linac commissioning include turn-on of the cavities and solenoids, turn-on and fast recovery for room temperature devices, and emergency shut down of linac devices. Additional automated tasks include conditioning of multipacting barriers in the cavities and calibration of the control valves for the pneumatic tuners. To ensure a smooth transition to operations, we are currently working on real-time health monitoring of the linac cryomodules, including critical signals such as X-ray levels, RF coupler temperatures, and cryogenic parameters. In this paper, we will describe our automation procedures, the implementation details, and the experience we gained.
 
slides icon Slides TH1C3 [1.966 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-HIAT2022-TH1C3  
About • Received ※ 21 June 2022 — Revised ※ 25 July 2022 — Accepted ※ 10 August 2022 — Issue date ※ 19 September 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)